Date activities Country Description Used material
2010 France  Pau - Langon: Dewatering activities for the dewatering of the highway A65 from Pau to Langon. Contractor: Eiffage Through deepwells, drainage, filters and many pumps.
2009-2010  Holland  Scheldegas (Wijngaarden - Westerschelde): Construction of a gas pipeline with a diameter of 1200 mm and a length of 75 km. Contractor: Nacap/Denys (Gasunie)  Through deepwells, drainage, filters and many pumps.
2009  Holland  Meeden - Ommen: Construction of a gas pipeline with a diameter of 1200 mm and a length of 55 km. Contractor: A.Hak (Gasunie) Through deepwells, drainage, filters and many pumps.
2009  Holland Annen: Construction of a water pipeline with a length of 13km. Contractor: Siers (WMD)   Through deepwells, drainage and many pumps
2009  Holland  Eemshaven: Dewatering for a new powerplant. Contractor: Köster Bau (RWE)  Through deepwells, drainage and many pumps
2009  Yemen  Middle East: Seweragesystem of 9 km, including inspection chambers.  Filters and pumps 
2008  England  Isle of Grain: Construction of a gas pipeline with a diameter of 900 mm and a length of 21 km. Contractor: Amec (National Grid)  Through deepwells, drainage and many pumps
Jan 2006 till Dec 2007 Wales Construction of a gas pipeline with a diameter of 1200 mm and a length of 120 km of Milford Haven to Aberdulais. Especially for this project we bought two trucks to assist in rough terrain (for pictures look at the item "Projects").

100 pumps with filters and pipelines, a crane and two trucks

View project

Dec 2005 till Mar 2006 Azerbaijan City Baku: Dewatering through a drilling machine. We also took care of the transport of pumps, filters and pipelines (you can also look at the item "Projects").

Drilling machine, pumps with electric engine, filters and pipelines

view project 

Jul 2004 till Dec 2005 Belgium City Zelzate: Construction of a 20 km long high pressure gas pipeline. We looked after the required drainage works (you can also look at the item "Projects").

Through deepwells, drainage, filters and dozens of pumps

view project

Jan 2004 till Dec 2004 Turkey City Posof: Construction of a pipeline of 286 km through Turkey. We looked after the required drainage works(you can also look at the item "Projects").

2 cranes, 130 vacuum pumps and many filters

view project